Non-Compliance detail


  
Summary
 
Licence number: 1802
Annual Return Start: 01 Jun 2014
Annual Return End: 31 May 2015
Date Received: 14 Jul 2015
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
P1.3 The existing flow meter at Point 10 has failed. The alternate flow calculation method in Section M6.5 has been used. Appropriate Action taken by licensee 1
L2.1 Nitrogen limit exceeded due to reduced treatment processes to accommodate a temporary aerobic digester to manage sludge loads during the anaerobic digester upgrade. Anaerobic digester and aeration to be upgraded. PRP to address non-compliance(s) issued 1
L4.1 Volume limit exceeded for Point 10 (Outfall Tunnel) due to heavy rainfall. Appropriate Action taken by licensee 1